Building with the Carpenter
Trinity has been involved annually with Habitat for Humanity since 1993. Since that time, Trinity teams have completed 23 new homes and one house rehab. Our most recent home was dedicated in June 2012.
2013 Habitat Build
Join us as we build a new, six-bedroom house for a grandmother, her four grandchildren, and two foster children. Their previous home was destroyed by tornadoes – and this new one will be complete in just under 3 months!
Individuals, families and small groups are encouraged to get involved, contact Team Co-Leader Barry Guynes, baguynes@comcast.net for specific details!
For a printable schedule, click here.
2013 Trinity Habitat Schedule
|
Trinity Tasks
|
| Tue, January 29, 2013 |
Clear warehouse and cut lumber for walls |
| Thu, January 31, 2013 |
Assemble lumber for walls |
| Sat, February 02, 2013 |
Construct walls |
| Fri, February 08, 2013 |
Deliver walls to construction site |
| Sat, February 09, 2013 |
Erect walls at construction site and attach exterior OSB and blue board of exterior walls |
| Tue, February 12, 2013 |
Begin placing trusses on house and attaching with hurricane ties |
| Thu, February 14, 2013 |
Finish erection of trusses on house attaching with hurricane ties |
| Sat, February 16, 2013 |
Place decking and tar paper on roof |
| Tue, February 19, 2013 |
Erect porch trusses covering with decking, put on tar paper and drip edge, install truss bracing and attic stairs. Call Don for HVAC roughin, plumbing and roofing. |
| Wed, February 20, 2013 |
HVAC roughin |
| Thu, February 21, 2013 |
Install exterior doors and windows. Begin electrical roughin and insulate exterior walls next to bath tubs |
| Fri, February 22, 2013 |
Electrical roughin |
| Sat, February 23, 2013 |
Begin siding the home, install deadwood, blocking, insulation baffles and tasks above not completed |
| Tue, February 26, 2013 |
Foam insulate the electrical and install insulation if electrical inspection is signed off |
| Thu, February 28, 2013 |
Final Preparation for Dry Wall |
| Sat, March 02, 2013 |
Finish vinyl siding, soffit and fascia on back and sides of home. Attach brick ties to front of house. |
| Mon, March 04, 2013 |
Drywall installation |
| Tue, March 05, 2013 |
Finish Vinyl Siding, Soffit and Fascia/Drywall installation |
| Thu, March 07, 2013 |
Clean house after drywall installation and begin painting interior and call for plumbing 2nd stage |
| Sat, March 09, 2013 |
Complete painting of interior of house and call for 2nd stage HVAC installation |
| Tue, March 12, 2013 |
2nd Stage Electrical, continue interior painting and trim installation |
| Thu, March 14, 2013 |
Initiate installation of vinyl flooring |
| Sat, March 16, 2013 |
Finish installation of vinyl flooring and begin install of interior doors and trim. |
| Tue, March 19, 2013 |
Continue stallation of trim and interior doors |
| Thu, March 21, 2013 |
Kitchen Cabinets, Bath Vanity and Accessories |
| Sat, March 23, 2013 |
Finish Window and Floor Trim Installation |
| Tue, March 26, 2013 |
Install Range Hood, electrical fixtures, etc. |
| Thu, March 28, 2013 |
Install Closet Bifolds and Closet Hardware |
| Sat, March 30, 2013 |
Complete interior trim work, clean floor in preparation for waxing, install shutters and mailbox |
| Tue, April 02, 2013 |
Develop Punch List |
| Thu, April 04, 2013 |
Polish floor |
| Sat, April 06, 2013 |
Landscape and clean home, install window blinds |
| Sun, April 07, 2013 |
Rain day make ups |
| Tue, April 09, 2013 |
Rain day make ups |